$13.5M project to focus on Wisconsin 29 interchanges this summer

7:13 AM, Apr. 1, 2013
Work on the Wisconsin 29 bridge project near Pamperin Park last November.
Work on the Wisconsin 29 bridge project near Pamperin Park last November.
  • Filed Under

Intersections west of Green Bay will be improved this summer as part of a $13.5 million project to make Wisconsin 29 a better highway.

State transportation officials this week are rolling out a construction schedule highlighted by the creation of an interchange at Wisconsin 29 and Brown County FF. Work would begin in July, with a bridge carrying FF over 29 slated to open in mid-2014.

Other work is planned this season for a stretch of the Wisconsin 29 corridor along the Hobart-Howard border, Wisconsin Department of Transportation officials said in an news release. Also planned: ...

What's your take on the Packers Family Night change?

Retrieving results.
Watching practice is fine.(Your vote)
15%
576 votes
I'd rather watch a scrimmage.(Your vote)
23%
856 votes
I don't want to pay to watch practice.(Your vote)
27%
1018 votes
It doesn't matter to me.(Your vote)
34%
1272 votes

Catch up on the latest in our pregame show every game day.

Football fans

If you've ever answered "Who has the ball?" with "It's halftime," you might recognize The Airhead. Check out the characters in our cartoon gallery of oddball fans.

Special Reports

ORDER YOURS

Football fans

If you've ever answered "Who has the ball?" with "It's halftime," you might recognize The Airhead. Check out the characters in our cartoon gallery of oddball fans.

Special Reports